OSB3D model
Louisiana Pacific OSB
OSB plant implemented in two phases, with re-engineering and tropicalization of a refurbished Dieffenbacher multi-opening press.
- Capacity
- 300,000 m³/year
- Implementation
- 2 phases
- Press
- Multi-opening
Project · OSB
FIG 01 Forming line building, before construction · Chilepanel, Chile
The Alerce project takes the OSB plant that Chilepanel operates in La Unión from about 80,000 to between 110,000 and 120,000 m³/year, with new areas for debarking, drying with emissions control, screening, fines grinding and blending. ProHolz is carrying out the basic and detailed engineering of the expansion, integrated with the engineering of the manufacturer of the new equipment.
ProHolz engineers the project and carries out technical inspection of the installation; procurement and construction stay with the client.
The plant was laser scanned, and ProHolz built the 3D model of the expansion on that point cloud. The interference report identified 30 points of conflict between the new areas and the operating line, from debarking to the press outfeed.
3D model of the new areas; foundations and structures for conveyors, silos, platforms and pipe racks; new electrical rooms, cable trays and cables.
Deluge, spark extinguishing, compressed air, dryer emissions, effluents, process water and resin, with line lists, valve lists and bills of materials.
Hood layout and structure, ductwork with fabrication drawings, and fan specification.
Design meetings every two weeks since January 2025.
Technical support during installation and, since June, resident inspection of mechanical and structural work.
Other projects
OSB3D model
OSB plant implemented in two phases, with re-engineering and tropicalization of a refurbished Dieffenbacher multi-opening press.
Pellets
One of the largest pellet plants in Chile, with a biomass boiler. Integration of the suppliers' designs, electrical engineering, piping and start-up support.
Investment values are approximate, for order of magnitude only.
Contact
A technical conversation defines the scope, the disciplines and the engagement model: EPCM, owner's engineering or value engineering.